Project Track Record
Click any project to expand details
Stone Oak Park & Ride
UNDERPERFORMINGOpened 2018
Investment
$32M
Promise
"When those kinds of investments were present, the demand just mushrooms"
— VIA CEO Jeff Arndt, Sept 2020
Reality
211 riders/day, max 65 cars observed in 400-space garage
-95% vs. capacity
Sources
Scobey Complex
FAILEDPurchased April 2017
Investment
$5.2M
Promise
"Transit-oriented community" with housing, offices, retail near Centro Plaza
— VIA Strategic Plan, 2017-2021
Reality
8 years dormant, VIA calls it "an eyesore"
N/A - Never built
Sources
Primo Routes 102 + 103
MET TARGETRoute 103: Jan 2019, Route 102: Aug 2019
Investment
$60M
Promise
4,500 riders daily combined
— VIA CEO Jeff Arndt, June 2016
Reality
~7,800 riders/day combined (Nov 2023)
+73% above projection
Green Line BRT
IN PROGRESSConstruction started June 2025
Investment
$481M
Promise
8,000 riders/day (vs. 4,500 current corridor)
— VIA Planner Art Herrera, Oct 2024
Reality
TBD - Service begins early 2028
Projecting +78% increase